Small Groups Building - Construction UpdateLearn More

Groups Building Construction Update - March 2024

Posted on

Exciting update on the new Small Groups Building!

We're thrilled to share the latest progress on the new small groups building! Here's a quick overview of what's been happening:

Brick Installation:  We're happy to report that the brick installation is progressing smoothly. By the end of next week, we anticipate completing or being very close to finishing the Thompson Lane side of the building.

Window Installation:  Our window installation is well underway. As of this week, approximately 50% of the windows have been installed with glass, bringing in natural light and enhancing the aesthetics of our space.

HVAC Progress:  All HVAC units have been successfully set up. Our team is diligently working towards securing permanent power by early April, with plans to have the HVAC system fully operational by mid-April.‌

Sidewalk Installation:  We're gearing up for the next phase of our exterior work. Sidewalk installation along the Thompson Lane side of the building is scheduled to commence in early to mid-April, enhancing accessibility and convenience.‌

Interior Drywall:  Inside the building, progress is steady with drywall installation. We're on track to finish enough drywall by mid-April, marking the beginning of the exciting painting phase.

We're truly grateful for the dedication of our construction team and the support of our church family as we move closer to completing this project. Stay tuned for more updates!